Port Hercule — la digue semi-flottante

Semi-floating dike of 352 meters and 160,000 tonnes towed to the Principality in 2002, which made it possible to double the reception capacity of Port Hercule.

Work352 meter semi-floating dike, 160,000 tonnes
Set upTowed to the Principality in August 2002, swung onto the platform in September 2002
Technical principleRock side hinge and eight anchor lines — “fixed water wall”
Successive namesQuai Rainier I (2008), Esplanade Stefano Casiraghi (2013)
EffectDoubling of port capacity
AddressPort Hercule, La Condamine, 98000 Monaco
DistrictPort Hercule
Checked on6 October 2026

In 2002, Monaco installed the largest semi-floating breakwater in the world in front of its port: 352 meters long, 160,000 tonnes, towed to the Principality and moored at the foot of the Rock.

A work, not an embankment

The technique distinguishes this dike from a simple embankment: it is semi-floating, held by a ball joint on the Rock side and eight anchor lines, and operates on the principle of the “fixed wall of water”. The Journal de Monaco publishes the report of the visit to the site by Prince Rainier III and Hereditary Prince Albert, on September 14, 2002, with the description of the work and its anti-corrosion protection — thirty tons of anodes for twenty-five years.

The effect is measurable: the reception capacity of Port Hercule has doubled.

Names which date the work

A detail that the archive allows us to follow: the dike was given names by successive municipal decrees. In 2008, the old southern dike became the Quai Rainier I and the northern counter-pier the Jetée Lucciana. In 2013, the upper part of the semi-floating dike was named Esplanade Stefano Casiraghi.

These acts of naming are valuable for a simple reason: they precisely date portions of work that nothing else allows us to place in time.

What Memoria doesn’t pretend to know

The date of launch of the project has not been found: the documents consulted only date back to March 2002, and the concessionaire only mentions “studies in the 1970s”. Nor is the date of completion established by an act. The sheet therefore publishes what is proven – the implementation of 2002 – and leaves the upstream in the shadows.

The facts are paraphrased; only the source is cited. A correction, a missing date? Write to Memoria.

The complete history, archive by archive

4 archives

2013

DevelopmentJournal de Monaco n° 8.124 — 7 juin 2013· 27 May 2013

The upper part of the dike becomes the Esplanade Stefano Casiraghi

Municipal decree no. 2013-1588 of May 27, 2013 gives the name Esplanade Stefano Casiraghi to the upper part of the semi-floating dike. A maritime engineering work thus receives a commemorative name – the act is published in the Journal de Monaco.

Read the cited source →

2008

DevelopmentJournal de Monaco n° 7.856 — 2008· 11 April 2008

Naming of the quays: Quai Rainier I and Jetée Lucciana

Municipal decree no. 2008-1318 of April 11, 2008 gives the name “Quai Rainier 1er” to the old south dike and “Jetée Lucciana” to the north counter-pier.

Memoria archive — source cited above

2002

ConstructionJournal de Monaco n° 7.566 — 27 septembre 2002· 14 September 2002

The 160,000-ton dike hinged to the median

On September 14, 2002, Prince Rainier III and Hereditary Prince Albert visited the construction site of the new seawall at Port Hercule: the 352-meter, 160,000-ton structure is hinged to the ground, with 30 tons of anodes planned for twenty-five years of protection against corrosion. The dike is semi-floating – a hinge on the Rock side and eight anchor lines – and operates on the principle of a “fixed wall of water”.

Read the cited source →
ConstructionJournal de Monaco n° 7.555 — 19 juillet 2002· 9 July 2002

The construction site regulated by ministerial decree

Ministerial decree No. 2002-421 of July 9, 2002 establishes a work zone with no public access in the port of La Condamine, in application of the sovereign order regulating the extension and redevelopment work zone of the port. A municipal decree of March 21, 2002 already regulated automobile traffic during this work: the acts have governed the construction site from the beginning of 2002.

Read the cited source →
Sources & press coverage

Sources cited in Port Hercule — la digue semi-flottante's timeline

Memoria paraphrases facts from these publications and links to their publishers. Titles and links remain the property of their authors; no article content is reproduced.