Home·Buildings·Land reclamation·Terre-plein de Fontvieille

Land reclamationFontvieille✓ Verified archive

Terre-plein de Fontvieille

The Principality's largest land reclamation: ground gained on Fontvieille bay from 1965, with the State buying back the land in 1973.

Founding domain actLaw No. 781 of 2 July 1965 decommissioning parcels of the public maritime domain
ConcessionTreaty of 2 August 1965 with SADIM — minimum area of 22 hectares
ApprovalSovereign Ordinance No. 3.663 of 10 November 1966
State buy-backLaw No. 939 of 16 July 1973 — loan of 50 million francs to acquire the land
First planning rulesSovereign Ordinance No. 5.583 of 16 May 1975
AddressFontvieille, 98000 Monaco
DistrictFontvieille
Checked on6 October 2026

The Fontvieille land reclamation is the largest sea extension in the Principality’s history. Before Mareterra, before Port Hercule, Monaco gained on Fontvieille bay the space where Louis II stadium, the heliport, the marina and an entire district stand today.

An operation in three stages

1965 — the decision. Law No. 781 of 2 July 1965 decommissions a parcel of the public maritime domain « for the construction of a land reclamation », about 14,700 m². One month later, on 2 August, a concession treaty is signed with SADIM: the parcel to be gained must reach a minimum area of 22 hectares, with a marina of at least 55,000 m², 500 m of quays and an eight-year completion deadline. The act states that « the first works date back to 1907 » — the idea of developing this bay is therefore much older.

1973 — the buy-back. Law No. 939 authorises the State to borrow 50 million francs to acquire « all the land of the land reclamation ». The Principality regains land control of what it had built.

1975 — planning. Ordinance No. 5.583 sets the first planning rules for the land reclamation: quality housing, shops, offices and hotels allowed, industry banned except naval and port activities. The district’s allocation is written in the act.

A floor-area discrepancy Memoria flags

Three figures circulate for Fontvieille’s area: 22 hectares in the 1965 treaty, 20 hectares in a 2016 National Council report, 17 hectares according to the concession holder. Memoria does not decide: it records all three and indicates their origin. An archive that silently chose one figure would create misleading precision.

What Memoria does not claim to know

The completion date of the works, the first stone and the volume of fill were not found in the acts consulted. The published timeline is that of decisions, which is solid — not that of the building site, which remains to be established.

The facts are paraphrased; only the source is cited. To suggest a correction or a missing date, write to Memoria.

The complete history, archive by archive

6 archives

1975

RegulationJournal de Monaco n° 6.139 — 1975· 16 May 1975

First planning rules for the land reclamation

Sovereign Ordinance No. 5.583 of 16 May 1975 sets coordination plan and planning, building and road rules for parts of the Fontvieille land reclamation not allocated to the State public domain. The text favours quality housing and allows shops, offices and hotels, banning industry except naval and port activities.

Memoria archive — source cited above

1974

DevelopmentJournal de Monaco n° 6.112 — 1974· 14 November 1974

New parcels decommissioned

Law No. 961 of 14 November 1974 decommissions two parcels of the Fontvieille land reclamation, of 45,119 m² and 14,022 m².

Memoria archive — source cited above

1973

RegulationJournal de Monaco n° 6.043 — 20 juillet 1973· 16 July 1973

The State buys back the land reclamation plots

Law No. 939 of 16 July 1973 authorises the State to borrow 50 million francs to acquire « all the land of the land reclamation » under the 1965 treaty, and allocates the land to the State public domain. This is when the Principality regains land control of the extension.

Read the cited source →

1966

RegulationJournal de Monaco n° 5.696 — 25 novembre 1966· 10 November 1966

Approval of agreements with SADIM

Sovereign Ordinance No. 3.663 of 10 November 1966 approves the concession treaty, the exchange of letters, the new port operating agreement and the specifications. The legal framework for the operation takes effect.

Read the cited source →

1965

FoundationJournal de Monaco — traité du 2 août 1965, approuvé en 1966· 2 August 1965

Concession treaty with SADIM: 22 hectares to be gained from the sea

On 2 August 1965, a land reclamation concession treaty is signed between the Domain and Housing Service and SADIM: a parcel to be gained from the sea in Fontvieille bay, with a minimum area of 22 hectares, with a new marina of at least 55,000 m² of water, quays 8 m deep over at least 500 m, and an eight-year completion deadline. The act's preamble notes that « the first works date back to 1907 ».

Read the cited source →
DevelopmentJournal de Monaco n° 5.624 — 9 juillet 1965· 2 July 1965

Decommissioning of a public maritime domain parcel

Law No. 781 of 2 July 1965 decommissions, « for the construction of a land reclamation », a parcel of the public maritime domain at Fontvieille — about 14,700 m² including the water area, protection dyke and careening basin — as well as the shore to the western boundary. Adopted on 25 June 1965, it is the founding domain act of the operation.

Memoria archive — source cited above
Sources & press coverage

Sources cited in Terre-plein de Fontvieille's timeline

Memoria paraphrases facts from these publications and links to their publishers. Titles and links remain the property of their authors; no article content is reproduced.